| Project name |
Employer |
Total estimate cost |
Contract & completion date |
|
|
| Private Avrasya Hospital |
AVRASYA Özel Sağlık Hizmetleri ve
Hastanesi A.Ş. |
2 532 566 YTL |
12.06.2006
23.11.2006 |
 |
|
| ERDEMIR 40MW Steam Turbine Generator Project |
SKODA POWER A.Ş. |
1.250.000 Euro |
24.04.2006
30.12.2006 |
 |
|
| Construction of Management Building |
ERDEMİR T.A.Ş. |
3 689 318 YTL |
06.10.2005 01.10.2006 |
 |
|
|
| CB4-CB5 Cranes OC1 Conveyor |
ERDEMİR T.A.Ş. |
116 367 YTL |
06.10.2005 01.10.2006 |
 |
|
|
| ERDEM?R Plate Rolling Mill |
ERDEMİR ERENCO A.Ş. |
412 130 YTL |
20.08.2005
18.12.2005 |
 |
|
|
Rolling Mills Region Coil Conveying and Sandblasting
Painting Facility |
ERDEMİR ERENCO A.Ş. |
12 474 922 YTL |
12.08.2005 03.02.2007 |
 |
|
|
| No. 6 Air Separation Plant |
ERDEMİR ERENCO A.Ş. |
3 381 318 YTL |
16.02.2005 16.02.2006 |
 |
|
|
Extension of Steelworks Charging Hall to south
|
ERDEMİR T.A.Ş. |
192 771 YTL |
27.04.2005 -
24.09.2005 |
 |
|
| Performance of some construction, disassembly and assembly works in billet casting plants |
İskenderun Demir ve Çelik A.Ş. |
1 044 000 YTL |
16.01.2003 28.xx.2003 |
 |
|
|
| Construction of zinc enrichment plant, turnkey contracting of material supply, mechanical, electrical and instrument assembly works |
Çayeli Bakır İşletmeleri A.Ş. |
266 744 USD |
02.01.2003 28.03.2004 |
 |
|
|
| Roofing and facing of the units in factory site and repair of downpipes, gutters and valley gutters |
İskenderun Demir ve Çelik A.Ş. |
168 214 YTL |
04.07.2002 20.01.2004 |
 |
| |
|
|
|
|
|
| |
|
|
|
|
|
|
| Construction of Istanbul Solid Waste Facilities, construction of the European Side final dumping area and medical waste burning facilities |
Nurol-Danwaste İş Ortaklığı |
27 858 YTL |
12.10.1993 31.12.1995 |
 |
|
|
| Manufacturing and assembly of steel construction for Erdemir Steel Service Centre |
Ereğli Demir ve Çelik Fabrikaları T.A.Ş. |
774 153 YTL |
16.05.2000 30.06.2002 |
 |
|
|
| Rough construction works of Corlu SSK Hospital with 260 bed capacity |
Unimar ve Trakya Elektrik A.Ş. |
746 800 USD |
28.11.2000 28.06.2002 |
 |
|
|
| Construction of infrastructure works for Dilovas? Port facilities |
Belde Liman İşletmeleri ve
Depoculuk A.Ş. |
3 525 750 USD |
24.02.2000 28.02.2002 |
 |
|
|
| Construction of Building and Equipment Foundations for Erdemir Steel Service Centre |
Öztaş İnşaat Malzemeleri Tic. A.Ş. |
617 315 YTL |
19.08.2000 16.12.2001 |
 |
|
|
| Assembly of work loader chrome plating building |
Ereğli Demir ve Çelik Fabrikaları T.A.Ş. |
15 364 YTL |
30.03.2000 04.10.2001 |
 |
| |
|
| Steel construction manufacturing and assembly for closed plate and RKK stock depot |
Ereğli Demir ve Çelik Fabrikaları T.A.Ş. |
543 087 YTL |
19.11.1999 16.08.2001 |
 |
|
|
| Construction of Kastamonu-Cide Vocational High School building |
T.C. Milli Eğitim Bak. ve Kastamonu
Valiliği, Bayram Yusuf Aslan |
227 700 YTL |
15.11.1999 30.06.2001 |
 |
|
|
| 8 year continuous primary education schools project 1st lot Bart?n/Merkez-Ulus-Cide |
Ekintaş İnşaat San. ve Tic. A.Ş. |
867 235 YTL |
03.02.1999 01.03.2000 |
 |
|
|
| Construction of Silivri warehouse and infrastructure facilities |
Ekintaş İnşaat San. ve Tic. A.Ş. |
540 890 USD |
01.09.1998 17.07.2000 |
 |
|
|
| Construction of new scrap preparation and storage facility |
Entes Endüstri Tesisleri İmalat ve
Montaj Taahüt A.Ş |
376 138 YTL |
07.07.1998 12.02.2000 |
 |
|
|
| 480 MW combined cycle plant |
Entes Endüstri Tesisleri İmalat ve
Montaj Taahüt A.Ş. |
108 243 YTL |
30.05.1997 20.02.2000 |
 |
|
|
| Construction of Cay?rova-Gebze factory of Cam ?? Madencilik Co. |
Nurol Çelik İnşaat Malz.
San. ve Tic. A.Ş. |
7 228 814 USD |
18.05.1996 01.10.1997 |
 |
|
|